Government Website icon

The .gov means it's official.
A .gov website belongs to an official government organization in the United States.

Padlock icon

The site is secure.
The https:// or lock icon ensures you're safely connected to the website and any information you provide is encrypted.

Publications iconKansas Register

Volume 40 - Issue 15 - April 15, 2021

(Published in the Kansas Register April 15, 2021.)

The Scoular Company

Request for Proposals

Interested parties are invited to submit a proposal to complete the below scope of repairs for the proposed The Scoular Company Goodland, Kansas project.

Scope of Work

The Scoular Company elevator track rehabilitation at Goodland, Kansas. Provide all necessary labor, equipment, and logistical services to supply all materials called for; complete all rehab and track construction work, ties, ballast, etc. The scope is further described as follows:

  • West switch to west end of grain silos:
    • furnish labor, equipment, and materials to install 45 new 6”x8”x8’6” ties
  • West end of silos to Main Street road crossing:
    • furnish labor, equipment, and materials to install 96 new 6”x8”x8’6” ties,
    • add new 1½” clean ballast, raise and tamp to proper height and cross-level
  • East switch to Main Street road crossing:
    • furnish labor, equipment, and materials to install 111 new 6”x8”x8’6” ties
  • Main Street crossing:
    • furnish labor, equipment, and materials to tear out and rebuild 65’ crossing: remove existing cross ties,
    • cut grade 18” below top of rail
    • install 39 new 6”x8”x8’6” ties
    • reinstall existing rail and OTM using new track spikes and AREMA grade bolts, nuts, and washers
    • add new 1½” clean ballast, rail and tamp to proper height and cross-level
    • install new timber crossing panels

MSA and Roadway Worker Protection

Contractors must complete, and have on file, a current Master Services Agreement with The Scoular Company before work begins.

  1. Contractors shall comply with all parts of 49 CFR Part 214 and 219 regarding FRA Roadway Worker Safety at all times. Men and equipment shall remain clear of the track unless they have gained Roadway Worker Protection from a qualified person.
  2. Contractor, contractor employees, agents, and/or subcontractors must be enrolled and comply with the FRA 219 approved drug testing program.
  3. Any subcontracted work will need to be approved prior to construction.

Work Windows

Impact to current railroad operations must be kept to a minimum. When work must take place that causes an active track to be taken out of service for the purposes of performing work that pertains to the project, the contractor must pre-arrange a defined work window with The Scoular Company. Contractor can anticipate a minimum work window of eight hours.

Standards

All standards referenced by the project plans and specifications, as well as all applicable AREMA standards, must be upheld during all phases of the project work, unless certain standards are excluded from the project with written approval. All rail shall be replaced at standard gauge of 56½.”

Submittals

The following documents shall be submitted by the contractor as part of the project, at the times listed:

  • Schedule of Work – submitted with proposal
  • Certificate of Insurance – submitted prior to construction
  • Safety Plan – submitted prior to construction
  • Proof of Roadway Worker Training – submitted prior to construction
  • All contractors must recognize this is a federal contract and agree to comply with federal requirements such as the Davis-Bacon Act, “Buy America,” and the Disadvantaged Business Enterprise (DBE), where applicable

Other Responsibilities

  • Permits – contractor is responsible for all federal, state, and local permits required for the work.
  • Utilities – contractor is responsible to locate and protect site utilities.
  • Site Clean-up – contractor is responsible for proper site restoration and proper disposal of materials removed in accordance with all local, state, and federal laws.

Insurance

Contractor shall purchase required coverage and submit for verification a Certificate of Insurance.

Materials

All materials shall meet the requirements found in the project plans and/or specifications as well as applicable AREMA requirements. Material storage is granted on railroad right of way to the contractor. However, no materials shall be stored closer than 15’ from the centerline of any active track at any time. Material and equipment laydown areas and reclaimed materials stockpiling locations shall be discussed and further clarified at the pre-proposal meeting. All removed materials remain property of The Scoular Company, to be stockpiled as directed by a representative.

Non-Project Areas

The Scoular Company has secured access to the project through the railroad right of way. Other access may be obtained by the contractor if he so chooses. All areas (public, private, and railroad right of way) that are used for access to the project, including parts of the railroad right of way which have no proposed work, shall be maintained and/or remediated, incidental to the project, by the contractor to the satisfaction of the property owner if any damage to these areas occurs.

Pre-Construction Meeting

The Scoular Company shall hold a pre-construction meeting at the project site to identify and mark ties that will be replaced.

Project Completion

All work pertaining to this project shall be completed by July 1, 2021.

Submission of a Proposal

All proposals must be submitted no later than April 30, 2021. All submitted proposals shall be reviewed by The Scoular Company. Please ensure your proposal includes all required information. All incomplete proposals shall be rejected. The structure of your proposal must be able to be clearly understood, all proposals shall provide the following line items and provide costs as required below:

  1. Provide a total sum of all line items on the proposal
  2. Mobilization and demobilization – lump sum
  3. Material (supply), labor (install), and equipment for each line item
  4. Tamp and regulate – lump sum
  5. Performance bond (sum not less than amount of awarded contract) – lump sum
  6. Clean up work site to completion – lump sum

Work Reporting

Daily work reports must be filled out and submitted to the designated Scoular representative. Weekly reports should include updates to project schedules, any delays, or any change in the scope of work. A detailed summary report must be submitted at the completion of the project.

Curtis Engel
Vice President/General Manager

Doc. No. 049042